|

| |

Burleigh
changes road plans
GORDON WEIXEL, Bismarck
Tribune
Published
Tuesday, July 19, 2005
By now, Burleigh County had expected to create a new
intersection on Bismarck Expressway connecting it directly to Yegen Road and
disconnecting it from Apple Creek Road using $300,000 in safety money from the
Department of Transportation.
But the Northern Plains Commerce Centre development forced the county engineer
to scrap his original plans and come up with something which will better match
the NPCC's needs, missing the April 1 bid letting. Currently, Apple Creek Road
intersects with Expressway just east of an overpass which restricts vehicle
sight lines. Apple Creek Road then intersects with Yegen near the Farmers
Livestock Exchange.
Burleigh's original plan, according to engineer Jon Mill, was to move the
intersection farther east and create a new half-mile, 40-foot graded section of
asphalt connecting directly with Yegen. The Apple Creek Road would have remained
open, but severed before reaching Expressway.
"The whole thing got severely confused by the
commerce center," Mill says. "The type of road we were putting in was
determined to be wrong for commerce center traffic. What we had planned was
something similar to Centennial, a nice wide two-lane asphalt section with
shoulders."
NPCC consultant Kadrmas, Lee & Jackson Inc. wants Yegen Road to be three
lanes, about 60 feet wide, according to KLJ engineer Brian Eiseman. It will be a
concrete section, eight to 11 inches thick, with a center turn lane, similar to
Bismarck's south 26th Street.
What Mill did was come up with a plan for the wider version that NPCC needs. It
calls for the new half-mile to be graveled, leaving NPCC responsible for the
concrete paving. The county was able to get an extension on the DOT's safety
grant and Mill says he plans to talk to commissioners at their first meeting in
August about bid letting and expects to open bids by mid-August.
"It's a short section and shouldn't take long to complete," Mill says.
"The contractor who gets the bid could probably start work a week after
August bid opening."
Until concrete for the new section is poured, it likely will be kept closed and
the Apple Creek intersection will continue to serve the local traffic.
Eiseman says the NPCC plans are complete and doesn't expect the road will be
closed very long. Presently, the route serves about 700 trucks a day, most
coming from Northern Improvement and Mariner Construction, according to KLJ
surveys, and NPCC is expected to start generating truck traffic of its own by
next spring.
Yegen Road will be reconstructed from Expressway to the Morrison Avenue
extension which is still on the drawing boards at KLJ. Morrison Avenue, which
will run east-west will intersect with Northern Plains Drive, also in the
planning stages. Northern Plains will provide direct access to NPCC, just east
of Sykes Enterprises.
The newly constructed section of Yegen from Expressway to Apple Creek road will
not have curb and gutter, but from the livestock exchange to Morrison Avenue
there will be curb and gutter, according to Eiseman. How much the road work will
cost is still being estimated, much of it depending on the thickness of
concrete.
Groundbreaking for NPCC is being planned for early August.
(Reach Gordon Weixel at 250-8255 or gordon.weixel@bismarcktribune.com.)

|